Fellbridge walkthrough · worked example
What if the evidence changed?
A walkthrough calls the east passage into question. The shelter has its own west route. Try changing the evidence to see which options would open.
Your assumptions
- Recorded as contested
Read the evidence
The joint walk-through found the east passage beside the entrance works narrower than the route plan showed. The proposed works boundary leaves insufficient clear width for the planned step-free passage. The daytime entrance approach cannot rely on EV03 until the route and boundary are clarified. The separate west route in EV09 is unaffected.
Fictional rehearsal update FSA-R4 · joint passenger-route walk-through, 30 October · EV03 - Recorded as unknown
Read the evidence
A requested window is not a committed window. The attractive combined package remains ineligible for this room's recorded choice.
Fictional operator request FSA-08; reply outstanding · EV04
Test confirmed evidence (7)
- Recorded as confirmed
Read the evidence
The main entrance stays open. No work is planned on the running railway in this demo.
Fictional station briefing, 23 October · EV01 - Recorded as confirmed
Read the evidence
The working area and existing doorway dimensions are recorded for the small entrance package.
Fictional survey sheet FSA-12, revision 2 · EV02 - Recorded as confirmed
Read the evidence
The temporary boundary, directional signs and staffed help point are shown together.
Fictional marked-up layout FSA-17, revision 1 · EV05 - Recorded as confirmed
Read the evidence
The supplier and planner share a 2 November delivery date for the shelter components. Dry assembly uses the west route in EV09, separately from the east entrance passage.
Fictional rehearsal packet FSA-R2 · supplier and planner agreement, 29 October · EV06 - Recorded as confirmed
Read the evidence
A station representative and passenger liaison are available for the sign and route rehearsal.
Fictional rehearsal roster, 23 October · EV07 - Recorded as confirmed
Read the evidence
One specialist is confirmed available for the proposed evening sequence on 4 November, within the eight team-day planning allowance. This fictional availability record does not grant access or authorise work.
Fictional resource note BR-06, 23 October · EV08 - Recorded as confirmed
Read the evidence
The shelter work area has a separate step-free approach from the west. The walk-through confirms the route can remain clear during dry assembly; it does not use the east passage beside the entrance works.
Fictional rehearsal packet FSA-R3 · west-route walk-through, 29 October · EV09
Delivery options
1 of 3 eligible on the recorded evidence